Birmingham to Crewe leg of HS2 delayed by further two years

Birmingham to Crewe leg of HS2 delayed by further two years

Ministers have agreed to delay the second of HS2 between Crewe and Birmingham amid soaring costs for the controversial high speed railway.

Transport Secretary Mark Harper said they will now prioritise the opening section, which means the completion and opening of Phase 2a to Crewe could be delayed by up to two years.

March 9, 2023
CEC to have greater say on HS2 construction and design

CEC to have greater say on HS2 construction and design

By Belinda Ryan, local democracy reporter
Cheshire East will have a greater say in decisions on HS2 construction and design after voting to become a ‘qualifying authority’.

The council is already a qualifying authority for phase 2a – the route between Birmingham and Crewe.

December 16, 2022
South Cheshire residents urged to air views on latest HS2 consultation

South Cheshire residents urged to air views on latest HS2 consultation

Crewe and Nantwich residents are being urged to have their say in the latest consultation for phase 2a of the HS2 scheme.

Phase 2a will connect the controversial high speed rail line to Crewe from Birmingham and Crewe.

February 11, 2021
HS2 Ltd announces “formal” start of construction of railway

HS2 Ltd announces “formal” start of construction of railway

HS2 Ltd has today announced the formal start of construction on the project which will eventually connect South Cheshire to London in under an hour.

It follows the announcement in April when Department for Transport gave approval for HS2 Ltd to issue Notice to Proceed to the four Main Works Civils Contractors working on the project.

September 4, 2020
Council to play bigger role in HS2 design through Cheshire

Council to play bigger role in HS2 design through Cheshire

By Stephen Topping, local democracy reporter
Cheshire East Council is set to play a key role in making decisions on HS2’s construction and design.

The council agreed on Thursday (July 18) to become a ‘qualifying authority’ for Phase 2a – the route between Crewe and Birmingham – in parts of the high-speed rail route that sit in the borough.

July 19, 2019
Cheshire East Local Plan may need revisit if HS2 hits Cheshire

Cheshire East Local Plan may need revisit if HS2 hits Cheshire

By Stephen Topping, local democracy reporter
Cheshire East Council chiefs could be forced to review their local plan if MPs give the green light for HS2 to hit Cheshire.

The authority adopted its local plan strategy for up to 2030 last July – three years after it was told to go back to the drawing board after submitting its first draft to the planning inspectorate.

October 17, 2018